September 2017: Construction Schedule


Post by: Eastlands Estate, 04 Sep 2017

BUILDING

WEEK 1: Finishing phase 4A, tiling phase 4B, construct rafts for storage garages

WEEK 2: Kitchens phase 4A, tiling phase 4B, brickwork for storage garage

WEEK 3: External groundworks phase 4A, landscaping phase 4A, ceilings phase 4C, external painting complete phase 4A

WEEK 4: Complete landscaping phase 4A, start internal finishing phase 4C

 

CIVIL

WEEK 1: Install curbs for roads phase 4A, install electrical reticulation phase 4A

WEEK 2: Install curbs for roads phase 4A, install electrical reticulation phase 4A

WEEK 3: Install paving phase 4A, install electrical reticulation phase 5A

WEEK 4: Install electrical installation phase 5A

 