October 2017: Construction Schedule


Post by: Eastlands Estate, 01 Oct 2017

BUILDING           

WEEK 1: S/O finishes phase 4A, late sales, external painting phase 4B, paving phase 4B

WEEK 2: Internal finishing phase 4B, level and shaping phase 4B, start rafts phase 5 and 4C

WEEK 3: Landscaping phase 4B, cabinetry phase 4B, final painting phase 4B, rafts phase 5 and 4C

WEEK 4: Handover phase 4B, internal finishing phase 4C, paving phase 4C, rafts phase 5 and 4C

 

CIVIL     

WEEK 1: Curbs phase 4B and C

WEEK 2: Curbs phase 4B and C, paving phase 4B and C

WEEK 3: Complete curbs phase 4C, paving phase 4B and C

WEEK 4: Complete paving phase 4C

               

               

 