November 2017: Construction Schedule


Post by: Eastlands Estate, 01 Nov 2017

BUILDING           

WEEK 1: Rafts phase 5A, brickwork phase 5A, finishing phase 4 A, B & C                  

WEEK 2: Landscaping phase 4C, rafts phase 5B, brickwork phase 5A, finishing phase 4 A, B & C                     

WEEK 3: Landscaping phase 4C, rafts phase 5B, brickwork phase 5A, finishing phase 4A, B & C, roofing garden apartments 4C                  

WEEK 4: Brickwork phase 5B, finishing phase 4A, B &C, roofing garden apartments 4C, plastering garden apartments 4C                          

CIVIL     

WEEK 1: Groundwork at storage garages

WEEK 2: Groundworks at storage Garages

WEEK 3: Curbing at Wild Peak Drive, paving at storage garages

WEEK 4: Paving Wild Peak Drive

 