May 2017: Construction Schedule


Post by: Eastlands Estate, 09 May 2017

BUILDING

WEEK 1  Handing over Phase 3A, Completing roofs Phase 3C, Start internal finishing Phase 3B

WEEK 2 Handing over Phase 3A, Completing roofs Phase 3C, Internal Finishing Phase 3B, External Works Phase 3B, Paving & Lawn Phase 3A2

WEEK 3 Internal Finishing Phase 3B, External Works Phase 3B, Landscaping Phase 3A2

WEEK 4  Handing over Phase 3A2, Internal Finishing Phase 3C, Rafts Phase 4A

 

CIVIL

WEEK 1 Completing roadbeds Phase 4, Stormwater Phase 4, Sewer reticulation Phase 4

WEEK 2 Completing roadbeds Phase 5, Stormwater Phase 5, Sewer reticulation Phase 5, Electrical reticulation Phase 4 - 6

WEEK 3 Stormwater Phase 6, Sewer Reticulation Phase 6, Electrical reticulation Phase 4 - 6

WEEK 4 Completing roadbeds Phase 6, Finishing of storm water Phase 4 - 6, Finishing of sewer lines Phase 4 - 6, Electrical reticulation Phase 4 - 6

 