March 2016: Construction Schedule


Post by: Eastlands Estate, 01 Mar 2016

BUILDING      

 Week 1: Pouring concrete rafts  

Week 2: Excavation rafts phase 1 B          

Week 3: Excavation rafts phase 1 B          

Week 4: Excavation rafts phase 1 C          

CIVIL:

Week 1: Asphalt external roads

Week 2: Starting construction of internal roads

Week 3: Road levelling and paving, main entrance

Week 4: Completing internal water and sewer reticulation