July 2017: Construction Schedule


Post by: Eastlands Estate, 17 Jul 2017

BUILDING

WEEK 1 Internal finishing phase 3C, paving phase 3C, brickwork phase 4A                              

WEEK 2 Internal finishing phase 3C, paving phase 3C, brickwork phase 4A, roofing phase 4A                          

WEEK 3 Internal finishing phase 3C, landscaping phase 3C, brickwork phase 4, plastering phase 4, roofing phase 4A                               

WEEK 4 Clean and handover phase 3C, brickwork phase 4, plastering phase 4, roofing phase 4

 

CIVILS

WEEK 1 All underground services complete, building platforms, roads and curbs to be done with construction                     

 