January 2016 Update


Post by: Eastlands Estate, 20 Jan 2016

We hope you had a wonderful holiday, and are rearing to go for the New Year.

We certainly did and are super charged for the year ahead, with a jam-packed schedule that promises to see us wrapping up Phase 1 and 2 and successfully   launching Phase 3, all within the next 12 months.

We kick off the year with an Estate exhibition at the Woolworths Court at Greenstone Shopping Centre, taking place from 12 to 25 January 2016. Pop in and visit our friendly sales team at the stand.

You can also visit our sales staff on site; our sales office at Eastlands Mature Lifestyle Estate is open seven days a week from 9am to 5pm.

JANUARY CONSTRUCTION SCHEDULE 

We resume work in earnest in January, beginning the third week of the month:

WEEK 3:
External civils: subbase on external roads. Internal civils: internal sewer reticulation, completion of brick work on the guard house, beginning of rafts for first 14 units

WEEK 4: 
External civils: continuing with subbase on external roads. Internal civils: internal roads construction, beginning of the guardhouse roof