February 2016: Construction Schedule


Post by: Eastlands Estate, 01 Feb 2016

BUILDING

WEEK 1: Excavation of rafts phase 1A

WEEK 2: Excavation, placing steel in rafts phase 1 A

WEEK 3: Pouring Concrete in rafts phase 1A

 WEEK 4: Starting brickwork in phase 1A

CIVIL

WEEK 1: Completion of curbs on external roads, installation of water and sewer lines internal phase 1

WEEK 2: Completion of the base layer of the external road

WEEK 3: Installation of water and sewer reticulation phase 1

WEEK 4: Tarring of the external road. Begin excavation for internal roads

 