August 2016: Construction Schedule


Post by: Eastlands Estate, 01 Aug 2016

BUILDING

Week 1 Final finishing phase 1B External work phase 1C  
Week 2 Painting phase 1C Internal finishing phase 1C External ground works phase 1C
Week 3 Completing phase 1B Painting phase 1C External ground works phase 1D
Week 4 Internal finishing phase 1D External ground works phase 1D   

CIVIL

Week 1 Platforms phase 2
Week 2 Curbs phase 1C Platforms phase 2 
Week 3 Paving roads phase 1C Platforms phase 2
Week 4 Platforms phase 2 

 